Project Description

Client: NPDC
Capacity: 8MMSCF
Status:
 ONGOING

The Egbema West AG Solution Gas Handling Facility is designed to gather and compress the existing flow-station LP and HP gas (ca. 8MMscf/d), treat the gas to required sales gas specification and deliver it at 42-43 barg to the NDPHC owned EIPP pipeline.

The Project Scope includes Engineering, Procurement, Construction, Installation and Commissioning for:

Main Process Skids
• Gas Compressor Unit
• Inlet Scrubber Unit
• Refrigeration Unit.
• Glycol Unit.
• Gas Metering Unit
• HCDP Control Skid.
• Fuel Gas Unit.
• Instrument Air Unit.
• Flare Unit.

Others
• Power Generators.
• MCC + Switchgear + UPS Package.
• 90 Days Reliability Run.

The design for the Egbema West AG GHF Project consistent with:

- Eliminating flaring of the gas produced from the flowstation.
- Supporting operability, maintainability and reducing NPDC’s OPEX.
- Supporting sustainable development of host community.
- Giving due focus to HSSE standards.
- Standardizing design template and equipment packages such that they can be modularised and be adapted for other locations.
- The needs for operational integrity throughout the projected minimum 30 years life cycle of the Facilities.
- The requirements of the gas customers, as specified in the gas sales contracts.
- Meeting the requirements of high availability, cost effective operations, minimum maintenance and environmental sustainability.
- Minimisation of site work to reduce exposure of personnel and equipment by driving off-site pre-fabrication and pre-commissioning of equipment packages.
- Designs to allow parts of the project to be fabricated and/or constructed as much as possible in Nigeria by Nigerian companies.
- Low operator intervention and minimised use of consumables.
- Optimum use of existing utilities and infrastructure.
- Flexibility with respect to future development scenarios.

Front End Engineering Design (FEED)
FEED completed to SHELL DEP by PROPAK. Oversight functions (review and approval functions) were provided primarily by MAKON and ultimately by SPDC-NPDC. All HAZOP report recommendations and action points completely closed out.

Detailed Engineering Design (DED):
DED being executed to International Standards and has progressed to 6% completion. MAKON and ENERFLEX will be responsible for the design and fabrication of the process-related equipment with SPDC-NPDC performing the oversight functions of reviewing documents& drawings and giving approvals.

As a result of the direct derivative of the FEED and DED, Procurement is divided into Major Equipment and Materials (Foreign Long Lead Items and Overseas Bulk items) and Minor Equipment and Materials (Local procurements). Detailed design of process packages are still ongoing and fabrication is yet to proceed.

Fabrication work will be succeeded by Factory Acceptance Tests (FAT), with the Clients SPDC-NPDC and other regulatory bodies such as NAPIMS and DPR in attendance. The procurement/fabrication of other skids and Utility vessels will be done in due course. As a NCD requirement, METS plan to fabricate various components and tanks locally.

Being a green field project, the Egbema West AG GHF Project will involve heavy construction activities. Collectively, a summary of the scope of construction activities for the AG facilities includes but not limited to:

- Site survey and Geotechnical studies
- Mobilization and Transport activities
- Surcharge Removal
- Mobilisation of Piling Works
- Piling and Installation of Pile casings in their required positions
- Prefabricate and install reinforcements on the installed piled casings
- Pile cap Construction of foundations as required for Piled Equipment
- Construction of raft foundation for skid and others as per AFC drawings
- Foundation for Equipment (piled)
- Construction of Temporary/ Permanent Site Access Roads within the facility
- Precast of Storm water drains.
- Precast of Pipe/Cable Sleepers.
- Fabrication & Installation of Cable Tray Steel Works on Sleepers.
- Several Excavation, Blinding & Installation activities.
- Pipe Rack Foundation.
- Precast Equipment Foundation.
- Piling for Equipment Foundations.
- Excavation & Installation of Precast Storm Water Drains.
- Pour Concrete & Install Rebar for Equipment.
- Installation of Precast Foundation.
- Concrete Road Works (All Areas).
- Erection of process skids, vessels and Equipment unto foundations.
- Installation of various instrument valves and fittings.
- Laying of instrument cables plant-wide.
- Installation and Hook-up of Electrical Buildings.
- Installation of Electrical Cables plant-wide.
- Deployment of Telecommunication equipment.
- Re-assembly of Accessories for Skids.
- Other miscellaneous activities to ensure mechanical completion.

METS aims to maintain the highest Health, Safety and Environment Standards with no Loss-Time Injury (LTI) when construction proceeds.